Estimate the quantity and cost of earthwork for a road section from the given data. 

The formation width of the road is 8 m. Side slope is 2:1 for both banking and cutting. The rate of earthwork is Rs. 150/m³.

Chainage 0+000 0+020 0+040 0+060 0+080 0+100 0+120

RL of ground level

123.9 125 124.6 122.9 121.60 121 120.4
RL of formation Level 123.2 123.6 124 123.6 123.2 122.8 122.4