Estimate the quantity and cost of earthwork for a road section from the given data.
The formation width of the road is 8 m. Side slope is 2:1 for both banking and cutting. The rate of earthwork is Rs. 150/m³.
| Chainage | 0+000 | 0+020 | 0+040 | 0+060 | 0+080 | 0+100 | 0+120 |
|
RL of ground level |
123.9 | 125 | 124.6 | 122.9 | 121.60 | 121 | 120.4 |
| RL of formation Level | 123.2 | 123.6 | 124 | 123.6 | 123.2 | 122.8 | 122.4 |